how to set up an electric vehicle charging station

Building an electric vehicle charging station is a process that involves multiple steps and considerations. Here are the detailed steps for building an electric vehicle charging station:

1. Preliminary preparation

Market research and demand analysis

Analyze the number, distribution and charging needs of electric vehicles in your area.

Investigate the layout and operation of competitors' charging stations.

Site selection and contract signing

Choose a suitable site, such as a public parking lot, shopping center, residential area, etc., to ensure that the site has sufficient power supply and convenient transportation.

Try to avoid areas with high public electricity consumption such as hospitals and government units.

Sign a charging pile construction contract with the site owner.

Understand relevant laws and policies

Before building a charging station, be sure to understand the relevant national and local laws and policies to ensure that it meets the construction standards and requirements.

Level-3-charging-(supercharge-DC-fast-charging).jpg

2. Application and approval

Project application

Submit an application for the charging station construction project to the local government or relevant department, including information such as the project name, construction location, and investment amount.

Provide relevant information, such as a project plan, land use right certificate, etc.

Acceptance review and planning approval

The local government or relevant department will accept and review the project application to review whether the project complies with relevant laws and policies.

If the project meets the requirements, planning approval will be carried out, including land use planning, power line planning, etc.

NDRC filing

Provide the telephone number and identity information registered with the legal person's ID card.

Submit the detailed address of the station, the number of charging piles, the cost planning and other information.

Provide the company's unified social credit code and complete the filing procedures.

Construction permit

After the planning approval is passed, obtain a construction permit and allow construction to start.

III. Construction and construction

Power application and construction

Bring relevant site certificates and filing documents to apply for power supply to the power department.

According to the power demand of the installed machine, apply for the corresponding power supply.

The power supply bureau will provide a suitable power supply plan and cost estimate.

Power facility construction

After obtaining the approval documents and construction plan from the power bureau, start the power facility construction.

You can choose to have the power bureau construct or a third party complete the power construction.

After the construction is completed, it will be inspected and confirmed by the power department.

Purchase and installation of charging pile equipment

According to the parking spaces and power conditions of the station, purchase suitable charging pile equipment.

Comprehensively consider the operation needs and the surplus power of the transformer, and choose an integrated or split charging pile.

Install charging pile equipment and conduct necessary debugging.

Equipment of supporting facilities

Customize awnings as needed to provide sunshade and shelter from rain.

Set up rest rooms to provide convenience for staff.

Consider adding vending machines and other related facilities according to the site conditions.

EV-charging-stations-1.jpg

IV. Acceptance and commissioning

Acceptance and commissioning

After the construction is completed, acceptance and commissioning are carried out to ensure that the charging station operates normally and meets relevant standards.

Commissioning

After obtaining the acceptance permit, it is officially put into use to provide charging services for electric vehicle users.

Operation management

Formulate reasonable charging prices and service policies.

Establish a sound operation management system to ensure the safe, stable and efficient operation of the charging station.

Ev-charging-station-Malaysia.jpg

V. Continuous optimization and upgrading

Continuously optimize the layout of charging stations and the performance of charging equipment according to market demand and technological development.

Strengthen cooperation with upstream and downstream enterprises in the industry chain such as electric vehicle manufacturers and charging service platforms to jointly promote the development of the electric vehicle charging infrastructure industry.

Through the above steps, a standard, safe and reliable electric vehicle charging station can be established to provide convenient and efficient charging services for electric vehicle users.

If you want to know more about "how to set up an electric vehicle charging station", you can consult us online or by email (sales@hjlcharger.com).

Recommended Reading

Get In Touch With Us

Whenever you need us, we're here for you. --- Contact us for all your support needs, from technology, general queries to information support, etc. Our hotline numbers and e-mail are open 24hx7d for your needs.

Copyright © 2023.Shenzhen Hongjiali New Energy Co., Ltd All rights reserved. Site Map back to home